The Omicron Chapter of Psi U has called 313 East Armory home since 1924. Designed by famed architect Benjamin Marshall, known for landmark Chicago area designs like the Drake Hotel and Cuneo mansion, the house is a campus jewel whose time has come for polishing. Work was completed in mid-August 2007 on the roof, safety concerns, and code compliance. Phase four, the Centennial Grill Project, completed in the Summer of 2010 in conjunction with the chapters Centennial Celebration and the hosting of the International Convention. Phase three saw the construction of a new sign & pavers at our corner, and the installation of a home theater system in the living room. Phase two cleaned up the alleys, sawt the installation of new oak flooring in the foyer, and remodeling of the Beta Chi bathroom/laundry area. The project started in 2007 with a new roof. Take a look at the job's progression here and in our photo gallery.
2010 - Installation of new gas grill with permanent gas line hookup and privacy fencing around the basketball court

2010 - Installation of new gas grill with permanent gas line hookup and privacy fencing around the basketball court

View more photos here.
2009 - Installation of New Sign and Pavers at Corner of 4th and Armory


2009 - Home theater system installed in living room
2008 - Installation of New Hardwood Flooring in Foyer and Dining Room

2008 - Resurfacing of South Alley
2007 - Installation of New Roof
2009 - Installation of New Sign and Pavers at Corner of 4th and Armory



2009 - Home theater system installed in living room

2008 - Installation of New Hardwood Flooring in Foyer and Dining Room


2008 - Resurfacing of South Alley

2007 - Installation of New Roof

Master Plan for Renovations - Gorski Reifsteck Architects
In preparation for our centennial anniversary and beyond, the Omicron Alumni Association moved in 2005 to retain Gorski Reifsteck Architects of Champaign, whose principals sit on the University of Illinois architecture faculty, to submit a master plan for renovations. Professor Stasz Gorski and Kevin Price of Gorski Reifsteck presented us their recommendations, and our alumni board approved taking out a $150,000 loan to fund the rehabilitation. In time, and with the continued support of our members, we are confident that we will succeed with the complete rehabilitation of our chapter house and secure the Omicron’s position on campus for the many years to come.
The report from Gorski Reifsteck Architects may be accessed via the following Word documents: Introduction to the Master Design Submittal and Master Plan - broken down by systems and components, with detailed cost analysis. Professor Gorski and Mr. Price explained there are three phases to the renovations:
The report from Gorski Reifsteck Architects may be accessed via the following Word documents: Introduction to the Master Design Submittal and Master Plan - broken down by systems and components, with detailed cost analysis. Professor Gorski and Mr. Price explained there are three phases to the renovations:
- Safety Issues and Code Compliance - to be Addressed Immediately (including the roof and decks)
- Monitor and Maintenance Priorities - to be Addressed in 1-2 Years
- Facility Improvements - to be Addressed as Budget Allows